We applied for new PNG Connection at Rannapark, Ghatlodia, Ahmedabad -380061 on 03 rd January along with the other applicants of the society. The supply in the entire society have started almost 1 year back but till date the supplies to our premises have not yet started.
Out of 12 members in our block, already 6 connections are working and remaining are pending since long. Many a times complaint for the same is done but NO proper response / action have been received / taken from the Company personnel. However, finally we decided to track the complaint. The below is the track record of the complaint made in June and the responses received.
Complaint No. : C100133499
Date Mode of Communication Responses
10-Jun-11 Customer Care Centre Will be completed in 1 week
24-Jun-11 Customer Care Centre Will be completed by 15th July
22-Jul-11 Customer Care Centre Will be completed by 31st July
10-Aug-11 Personal visit to Gurukul office - Met Cust Care Executive - Ms. Jayshree Raval Will be completed immediately
24-Sep-11 Personal visit to Gurukul office - Met Cust Care Incharge - Mr. Anush M Will be completed ASAP and atleast will inform about the reasons for delay, if any
I was assured by the Customer Care Incharge Mr. Anush M on 24 th September that I will be informed about the status of the work and also the reason for delay if any. But till date there is no update either in the work nor the reasons.
The Pipeline and meter work is already completed long back. But I don’t know what is the problem that the company is yet not starting the connection?
Request to look in to the matter and arrange for starting the connection IMMEDIATELY.