My mother bought a 3BHK flat from a Company named Keppel - Purvankara- in July
This company promised a signed contract to hand over the flat latest by Dec a grace period of 6 months inclusive. In the event of failure to do so, the company promised to pay a sum of 6000 per month until the completion.
Today is 30 Dec and the flat hand over has not happened yet. The real estate price has gone up 4 times in the area where the flat is, but the compensation amount remains 6000. Plus KPTCL charges have been increased as per the revised rates of 2011.
Ultimately, my mother has had to pay the higher amount than what she would have to pay if the flat was handed over on time.
This complaint is to take a strong action on the builder for the following reasons-
- Even after 2 years on the agreed date of handover, the flat is still not ready
- the compensation amount remains 6000 though the current rent in that area is 24000 for 3 BHK
- there is no genuine response from Keppel - Purvankara despite regular follow-up from my mother
- consistent harassment by keppel-purvankara finance dept and handover dept in event of asking the handover of the flat
Address of the Flat-
Flat # B1 - 0202
Elita Promonade
J.P nagar 6th Phase
Bangalore - 560068